SECURITIES AND EXCHANGE COMMISSION
                             Washington, D.C. 20549



                                    FORM 8-K

                                 CURRENT REPORT
                     PURSUANT TO SECTION 13 OR 15(d) OF THE
                         SECURITIES EXCHANGE ACT OF 1934

         Date of Report (date of earliest event reported): June 26, 2001

                                RAYTHEON COMPANY
             (Exact name of registrant as specified in its charter)


     Delaware                1-13699                      95-1778500
     --------                -------                      ----------
(State of Incorporation)   (Commission File Number)    (IRS Employer
                                                       Identification Number)

                                141 Spring Street
                         Lexington, Massachusetts 02421
                         ------------------------ -----
               (Address of principal executive offices (Zip Code)

       Registrant's telephone number, including area code: (781) 862-6600

1 Item 5. Other Events. On June 26, 2001, the Registrant announced that it had received third party estimates indicating higher costs to complete two Massachusetts construction projects for Sithe Energies, Inc. that were abandoned by Washington Group International. Registrant is completing the construction projects pursuant to performance guarantees. In connection with this announcement, the Registrant issued a press release, a copy of which is attached hereto as Exhibit 99.1 and is specifically incorporated herein by reference, and the foregoing description is qualified in its entirety by reference to such press release. Item 7. Financial Statements, Pro Forma Financial Information and Exhibits (c) The following exhibits are filed as part of this report: 99.1 Press release dated June 26, 2001. 99.2 Chart of Exposure Summary. SIGNATURE Pursuant to the requirements of Section 12 of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned hereunto duly authorized. Dated: June 26, 2001 RAYTHEON COMPANY By: /S/ John W. Kapples John W. Kapples Vice President and Secretary

1 EXHIBIT LIST Exhibit No. Description 99.1 Press Release Dated June 26, 2001 99.2 Chart of Exposure Summary

1 EXHIBIT 99.1 News release FOR IMMEDIATE RELEASE Contacts: David Polk (News Media) 781.860.2386 Timothy Oliver (Investor Relations) 781.860.2167 Raytheon sees higher costs to complete two Massachusetts construction projects LEXINGTON, Mass., (June 26, 2001) - Raytheon Company (NYSE: RTN) today announced that it has several preliminary estimates of the cost to complete two Massachusetts construction projects for Sithe Energies Inc., that were abandoned by Washington Group International (WGI) and which Raytheon is completing pursuant to performance guarantees. Some of these preliminary estimates assume significant increases in liquidated damages, construction management costs and project contingencies, which would cause the total liability to be higher than the March 2001 estimate. Raytheon now expects the eventual liability on these two projects to range between $450 million and $700 million, compared to the earlier estimate of $325 million. Raytheon has assembled a team of project management experts to conduct critical reviews of the construction schedule associated with each of the estimates it has received. Optimizing the construction schedule would have a material favorable impact upon the size of any incremental charges related to the Sithe projects. "What is most important is that the Raytheon team focuses its full attention on getting these projects back on schedule in order to minimize the impact of WGI's abandonment," said Daniel P. Burnham, Raytheon's chairman and chief executive officer. "Further precision with respect to both timing and cost will require completion of a more refined construction schedule." As previously disclosed, Raytheon sold its engineering and construction business to WGI on July 7, 2000, and had guaranteed performance of certain projects to the project owners. WGI announced in March 2001 that it had severe liquidity problems. Raytheon took over performance of the two Sithe projects in March 2001, following the abandonment and default by WGI of its obligations with respect to those projects. Raytheon previously disclosed a potential liability of up to $450 million for 50 construction projects for which it has performance guarantees, including $325 million for the two Sithe projects. As was described at the time, Raytheon's analysis was based on estimates provided by WGI of the cost to complete them. Under the sale agreement for Raytheon's former engineering and construction business, WGI is required to indemnify Raytheon for all amounts expended by Raytheon to complete the projects, and Raytheon is entitled to full cash reimbursement for these amounts and full set-off against any WGI claims against Raytheon. Due to the bankruptcy filing by WGI, Raytheon does not intend to recognize for accounting purposes the value of its claims against WGI, although it intends to pursue all avenues to maximize its recovery. With headquarters in Lexington, Mass., Raytheon Company is a global technology leader in defense, government and commercial electronics, and business and special mission aircraft. Note: Raytheon will hold a teleconference beginning at 8:00 a.m. EDT to review the Sithe projects and other issues related to its former engineering and construction business on June 27. The dial in number for the call is 212-231-6022. There will also be a live webcast of the call available at www.raytheon.com. Forward-looking statements This news release contains forward-looking statements within the meaning of the Private Securities Litigation Reform Act concerning the company's financial results, future plans, objectives and expected performance. Specifically, statements in this release that are not historical facts, including statements accompanied by words such as "believe," "expect," "anticipate," "estimate," "intend," or "plan" are intended to identify forward-looking statements and convey the uncertainty of future events or outcomes. The company cautions readers that any such forward-looking statements are based on assumptions that the company believes are reasonable, but are subject to a wide range of risks, and actual results may differ materially. Important factors that could cause actual results to differ include, but are not limited to: the effects of WGI's bankruptcy filing; the final determination by the company of the required expenditures to complete the projects, the confirmation of the actual physical progress completed at the time of WGI termination, the impacts associated with the re-mobilization of the projects and WGI compliance with its contractual obligations and cooperation with Duke Fluor Daniel in its assumption of the construction activities. Further information regarding the factors that could cause actual results to differ materially from projected results can be found in the company's most recent filings with the Securities and Exchange Commission, including Raytheon's Form 10-K for the year ended December 31, 2000 and Form 10-Q for the quarter ended April 1, 2001.



EXHIBIT 99.2

Exposure Summary - Discontinued Operations
(Preliminary Estimates)


                                              Cash ETC
                                           Prior    Current      Q2 P&L      Cash Portion
($ Millions)                              Estimate  Estimate     Impact   Total    2001
                                                                   
Guaranteed Projects (50)
 Operations and Maintenance (33)             $0         $0         $0       $0     $0
 Engineering/Procurement/Construction (17)
   SITHE Projects (2)                      $325    $450-700      $125     $125     $0
   Others (15)                           $0-125     $36-125       $36      $36    $25
                                       --------    --------      ----     ----    ---
        Subtotal                       $325-450    $486-825      $161     $161    $25


Indemnified Projects (4)                                          $40      $40     $36
Retained Assets                                                   $71      $0       $0
Purchase Price Adjustment                                          $0      $0       $0
                                                                 ----    ----      ---
        Total                                                    $272    $201      $61